Skip to content
HazardClock

HHSRS Hazards and Awaab's Law Phase 2

By Crocker Digital Ltd · Published · Last reviewed

If you manage social housing in England, HHSRS is the framework that decides whether something in a property counts as a hazard — and since Awaab's Law arrived, it is also the framework that decides whether a repair report starts a statutory clock.

Two things are new in 2026. The hazard list itself was consolidated in June, and Awaab's Law Phase 2 brings a larger slice of it into the statutory repair deadlines. This post covers what HHSRS hazards are, what changed, and which ones matter most to a social landlord right now.

Phase 2's start date is 30 November 2026. That is the date in the amending Regulations (regulation 1(2) of the draft reads "These Regulations come into force on 30th November 2026") and the date GOV.UK gives. Those Regulations have legal effect only once they are made. Their legislation.gov.uk page shows whether that has happened.

What HHSRS Is

The Housing Health and Safety Rating System is the risk-assessment framework introduced under the Housing Act 2004. Rather than listing minimum standards a property must meet, it assesses the risk of harm a particular deficiency poses to an actual or potential occupier.

Section 2(1) of the Act defines a hazard as:

any risk of harm to the health or safety of an actual or potential occupier of a dwelling or HMO which arises from a deficiency in the dwelling or HMO or in any building or land in the vicinity

That framing matters. The same physical defect can be a serious hazard in one property and a minor one in another, depending on who is likely to be affected and how badly. A steep staircase without a handrail scores differently in a family home than in a single-occupancy flat.

Category 1 and Category 2 Hazards

Assessed hazards fall into one of two categories. Section 2 of the Act defines a category 1 hazard as:

a hazard of a prescribed description which falls within a prescribed band as a result of achieving, under a prescribed method for calculating the seriousness of hazards of that description, a numerical score of or above a prescribed amount

A category 2 hazard is the same thing scoring below that threshold. In plain terms: the assessment produces a numerical score, and the score decides the category.

The practical difference is enforcement, and it sits in two separate sections. Section 5(1): "If a local housing authority consider that a category 1 hazard exists on any residential premises, they must take the appropriate enforcement action in relation to the hazard." Section 7(1), by contrast, says the listed provisions "confer power on a local housing authority to take particular kinds of enforcement action" for a category 2 hazard. So: a duty on category 1, a power on category 2. For a social landlord, that distinction sits alongside — not instead of — the Awaab's Law duties, which run on their own trigger and their own clocks.

What Changed in June 2026

HHSRS carried 29 separate hazard descriptions from 2006 until this year. That list was consolidated.

The Housing Health and Safety Rating System (England) (Amendment) Regulations 2026 (SI 2026/571) amend Schedules 1 and 2 of the 2005 Regulations. Regulation 8 works mainly by omission and insertion, with one substitution: reg 8(k) replaces "the dwelling or HMO" with "a building" in paragraph 29, broadening structural collapse and falling elements — a Phase 2 hazard — beyond collapse of the dwelling itself. Regulation 1 states:

These Regulations come into force on 23rd June 2026.

Regulation 8 omits thirteen paragraphs — "omit paragraphs 5, 6, 9 and 10", "omit paragraphs 15, 16 and 17", "omit paragraphs 19 and 20", "omit paragraph 24", "omit paragraphs 26 to 28" — and inserts five new consolidated descriptions in their place:

New paragraph Heading (verbatim) Replaces
4A Indoor Air Pollutants 5 Biocides, 6 Carbon monoxide and fuel combustion products, 9 Uncombusted fuel gas, 10 Volatile organic compounds
14A Domestic Hygiene 15 Domestic hygiene, pests and refuse, 16 Food safety, 17 Personal hygiene, sanitation and drainage
18A Falls on the level 19 Falls associated with baths etc, 20 Falling on level surfaces etc
23A Fire and explosions 24 Fire, 27 Explosions
25A Collisions, Entrapment and Ergonomics 26 Collision and entrapment, 28 Position and operability of amenities etc

On the count of 21: neither the instrument nor its Explanatory Note states a number — the Note says only that it "amalgamates some of those descriptions". 21 is arithmetic on the operative text above: 29 as made, minus the 13 omitted, plus the 5 inserted. We give the derivation rather than the bare figure because the counting convention is not the source's; new paragraph 14A alone carries six sub-paragraphs that were previously spread across three numbered descriptions.

One merger people get wrong: paragraph 25, "Flames, hot surfaces etc", is not omitted and not consolidated. It survives unamended. What merged under the fire heading was paragraph 24 (Fire) with paragraph 27 (Explosions). The underlying risks did not go away; the list that describes them got shorter.

⚠️ If you hold a document, a tool or a policy that lists 29 HHSRS hazards, it predates 23 June 2026. That includes a good deal of guidance still circulating online, and a fair number of internal procedure documents. Check the source date before relying on any enumeration.

The table above gives the omissions and insertions verbatim from regulation 8, which is what you need for a mapping exercise. We are not reproducing the full renumbered list of surviving descriptions here: secondary summaries of the consolidation disagree with one another on headings, and if you are re-labelling your own categories you should work from the amended Schedule 1 directly on legislation.gov.uk rather than from any summary — including this one.

A Note On The "Four Hazard Groups"

You will see HHSRS descriptions presented in four groups — physiological, psychological, protection against infection, protection against accidents. That grouping is worth understanding, but it is worth knowing where it comes from: it is a feature of the HHSRS Operating Guidance, not of the Regulations. Schedule 1 as made is a flat list of 29 numbered descriptions carrying no four-group headings. The amending instrument does not introduce that grouping either, though it does give each inserted paragraph its own heading — "Indoor Air Pollutants", "Domestic Hygiene", "Falls on the level", "Fire and explosions", "Collisions, Entrapment and Ergonomics".

We have removed the grouped enumeration that previously appeared here. It listed "domestic and personal hygiene, food safety, sanitation and drainage" as separate members — the exact paragraphs 15, 16 and 17 that regulation 8 omitted and merged into 14A — which is precisely the pre-June-2026 enumeration this post warns against.

If you want to see how a given hazard maps to the Awaab's Law phases, the phase checker covers the assignments.

Which HHSRS Hazards Awaab's Law Covers

This is where HHSRS stops being a background framework and starts driving statutory deadlines.

Phase 1, in force since 27 October 2025, covers damp and mould growth, plus emergency hazards. "Emergency hazard" is wide but not unlimited — regulation 3(2) of SI 2025/1042 requires that for an emergency hazard "the risk of harm is not associated with a lack of adequate space for living and sleeping (or either of those things)", so it reaches every prescribed hazard except crowding and space.

Phase 2, from 30 November 2026, extends the same timescales to a wider set. The GOV.UK collection lists them as:

excess cold, excess heat, falls on the level (including falls on the level, falls on stairs, etc, and falls between levels), structural collapse, fire and explosions, electrical hazards, domestic hygiene (including personal hygiene and food safety)

That list maps onto the amended Schedule 1 through the draft Amendment Regulations, reg 3(3)(c)(ii), which names the prescribed paragraphs directly — "paragraph 2, 3, 14A, 18A, 21, 22, 23, 23A or 29 of Schedule 1" (excess cold, excess heat, domestic hygiene, falls on the level, falls on stairs, falls between levels, electrical hazards, fire and explosions, structural collapse), alongside damp and mould.

"Fire and explosions" carries a statutory carve-out. Regulation 3(3)(b) inserts a definition of "excluded fire hazard" — fire risk that "arises from a deficiency in a FSO-regulated part of a building that contains two or more sets of domestic premises" — and 3(3)(c)(i) inserts "that is not an excluded fire hazard" into the opening words of sub-paragraph (a) of the definition of "relevant hazard" ("is a prescribed hazard where—"), above both the significant and the emergency limb. GOV.UK's Phase 2 guidance states the effect: "Awaab's Law applies to fire hazards within individual flats and homes which are not currently covered by the FSO." From their start date (30 November 2026), the Phase 2 amending Regulations take fire hazards arising from a deficiency in the parts of a building with two or more homes that the Fire Safety Order covers (the structure, outside walls with their windows and doors and anything attached such as balconies, shared areas, and flat front doors) out of Awaab's Law, including the 24-hour duty. While those Regulations are not in force, the 24-hour duty still covers these hazards where you are responsible for that part of the building. Either way, report them to the building's Responsible Person under the Fire Safety Order, or deal with them under that Order if you are the Responsible Person.

Phase 3 is planned to add the remaining HHSRS hazards except overcrowding. GOV.UK has said 2027, but no draft Phase 3 regulations have been published and no start date has been set.

So the direction of travel is that HHSRS and Awaab's Law converge: eventually almost the whole framework carries statutory repair deadlines rather than only enforcement exposure.

For the start date and whether the amending regulations have been made, see the Phase 2 start date and hazard list.

The Threshold That Actually Matters

There is a trap here worth naming, because it catches people who know HHSRS well.

Awaab's Law does not key off the category 1 / category 2 distinction. Its trigger is whether a hazard presents a significant risk of harm, which is its own test. A hazard can be relevant to Awaab's Law without a formal HHSRS scoring exercise having been carried out, and the ten-working-day investigation clock starts from the point of awareness — not from the point at which someone completes an assessment.

In practice that means you cannot wait for a formal HHSRS score before starting the clock. The classification decision has to be made quickly, on the information available, and recorded. A written triage rule — decided in advance, applied consistently, and recorded — is what makes that defensible. For a worked version of that rule, see triaging Awaab's Law Phase 2 hazards.

Common Questions

How many HHSRS hazards are there? SI 2026/571 does not state a number. Counting the operative amendments — 29 descriptions as made, 13 omitted by regulation 8, 5 inserted — gives 21 since 23 June 2026. Sources published before that date will say 29.

What is a category 1 hazard? One whose assessed score reaches or exceeds the prescribed threshold in section 2 of the Housing Act 2004. Local authorities "must take the appropriate enforcement action" on category 1 hazards (section 5(1)); for category 2 hazards section 7(1) confers a power rather than a duty.

Does a category 2 hazard start an Awaab's Law clock? Possibly. Awaab's Law runs on whether the hazard presents a significant risk of harm, not on the HHSRS category. Do not use the category as your Awaab's Law trigger.

Which HHSRS hazards does Awaab's Law cover? Phase 1 covers damp and mould, plus emergency hazards. Phase 2 adds seven hazard groups to the significant-hazard timescales: excess cold, excess heat, falls (on the level, on stairs and between levels), structural collapse, fire and explosions, electrical hazards, and domestic hygiene. Fire hazards from a deficiency in the parts of a building with two or more homes that the Fire Safety Order covers are excluded. Phase 2's start date is 30 November 2026, the date set by the Phase 2 amending Regulations. Those Regulations have legal effect only once they are made, and their page on legislation.gov.uk shows whether that has happened. Phase 3 is planned to add the remaining HHSRS hazards except overcrowding. GOV.UK has said 2027, but no draft Phase 3 regulations have been published and no start date has been set.

What To Do With This

If you are preparing for Phase 2, the HHSRS angle gives you two concrete jobs:

  1. Check your hazard reference material is post-June 2026. Any list of 29 is out of date, and if it is embedded in a triage form or a training pack it will quietly produce wrong answers.
  2. Map your own repair categories onto the Phase 2 hazards, not onto HHSRS as a whole. Seven groupings drive your statutory deadlines from 30 November; the rest of the framework does not, yet.

Work through the case lifecycle with the compliance checklist, see the Awaab's Law Phase 2 readiness plan for the week-by-week version, and use the checklist for the Phase 2 start for the final checks.

Keeping hazard classifications, phase assignments and statutory clocks aligned across a live caseload is the problem HazardClock is planned to solve. Join the waitlist — one email when HazardClock opens.

This is general guidance for registered providers and social landlords in England, not legal advice. HHSRS assessment is a technical exercise — where a formal rating is required, use a competent assessor. Always confirm the current hazard descriptions against the amended Regulations.

Last reviewed: 13 November 2026.

Sources

Stop tracking Awaab's Law deadlines in spreadsheets

HazardClock will calculate every Awaab's Law deadline automatically, send countdown alerts before they expire, and build an audit trail for investigations.